Project Updates

Current Status

December 18, 2025

FERC issued amended certificate

November 12, 2025

NC DEQ issued water quality certification

October 3, 2025

FERC issued Environmental Assessment

July 9, 2025

FERC EA schedule noticed

February 3, 2025

Amendment application filed: (CP25-60-000) to reflect the reduced scope (31 miles) and design changes. elibrary.ferc.gov

December 19, 2023

Certificate extension order: elibrary.ferc.gov

June 2020

FERC certificate issued (original project): (CP19-14-000). permits.performance.gov

Timeline & Milestones

2018–2020

Pre-filing, DEIS/FEIS, original certificate

2023

Certificate extension

2025

Amendment filed (CP25-60)

Late 2025

Issuance of Amended Certificate (target)

2026

Target construction start (subject to approvals)

2028

Target in-service